COHASSET POLICE STATION - 135 KING STREET

Finance & Cost

Explore the project financial impact and the appropriation request for the Cohasset Police Station at 135 King Street.

Estimated Total Project Cost

$31,300,000

Expenditures to Date

$5,400,000

Balance Available from
Original Appropriation

($5,000,000)

Appropriation Being Requested - 2026 Town Meeting

$20,900,000

Access the Tax Calculator to understand how this project will impact your taxes.

Expenditures to Date

The table below shows the costs already incurred and funded by the original appropriation.

Item Amount
Purchase of 135 King Street $2,400,000
Previous Designs, Studies, Engineering, Project Management, and Architects $3,000,000
Total Expenditures to Date - Funded by Original Appropriation $5,400,000

The table below shows the estimated project costs and funding comparison for May 2026 and October 2026.

Cost Comparison

Item May 2026 Oct 2026
Estimated Expenditures Remaining $25,083,000 $25,900,000
Balance Available from Original Appropriation ($5,000,000) ($5,000,000)
Appropriation Being Requested - 2026 Town Meeting $21,783,000 $20,900,000

These calculations show the total project cost and how the October 2026 appropriation request is determined.

How the Numbers Work

$5,400,000

Expenditures to Date
(funded by original appropriation)

Blue cross symbol on a white background

$25,900,000

Estimated Expenditures
Remaining

$31,300,000

Estimated Total
Project Cost

Image of a code snippet showing an HTML select element with a label and options.

$25,900,000

Estimated Expenditures
Remaining

Diagram illustrating the assembly of a mechanical component with labeled parts and instructions

$5,000,000

Balance Available from
Original Appropriation

Diagram showing a vertical pole with a spotlight attached to it, casting light onto a person standing below.

$20,900,000

Appropriation Request
(2026 Town Meeting)

What Residents Should Know

The total estimated project cost is $31.3 million.

This includes all costs, including amounts already spent and estimated costs to complete the project.

Of that amount, $5.4 million has already been spent from the original appropriation.

This includes the purchase of 135 King Street and previous designs, studies, engineering, project management, and architects.

The Town still has $5.0 million available from the original appropriation.

A balance of $5,000,000 remains available from the original appropriation

The amount being requested at Town Meeting is $20.9 million.

This request, combined with the remaining $5.0 million, will allow the Town to complete the project.

Savings from plan reductions are directly impacted by rising construction costs over time and additional design + OPM fees.