COHASSET POLICE STATION - 135 KING STREET
Finance & Cost
Explore the project financial impact and the appropriation request for the Cohasset Police Station at 135 King Street.
Estimated Total Project Cost
$31,300,000
Expenditures to Date
$5,400,000
Balance Available from
Original Appropriation
($5,000,000)
Appropriation Being Requested - 2026 Town Meeting
$20,900,000
Access the Tax Calculator to understand how this project will impact your taxes.
Expenditures to Date
The table below shows the costs already incurred and funded by the original appropriation.
| Item | Amount |
|---|---|
| Purchase of 135 King Street | $2,400,000 |
| Previous Designs, Studies, Engineering, Project Management, and Architects | $3,000,000 |
| Total Expenditures to Date - Funded by Original Appropriation | $5,400,000 |
The table below shows the estimated project costs and funding comparison for May 2026 and October 2026.
Cost Comparison
| Item | May 2026 | Oct 2026 |
|---|---|---|
| Estimated Expenditures Remaining | $25,083,000 | $25,900,000 |
| Balance Available from Original Appropriation | ($5,000,000) | ($5,000,000) |
| Appropriation Being Requested - 2026 Town Meeting | $21,783,000 | $20,900,000 |
These calculations show the total project cost and how the October 2026 appropriation request is determined.
How the Numbers Work
$5,400,000
Expenditures to Date
(funded by original appropriation)
$25,900,000
Estimated Expenditures
Remaining
$31,300,000
Estimated Total
Project Cost
$25,900,000
Estimated Expenditures
Remaining
$5,000,000
Balance Available from
Original Appropriation
$20,900,000
Appropriation Request
(2026 Town Meeting)
What Residents Should Know
The total estimated project cost is $31.3 million.
This includes all costs, including amounts already spent and estimated costs to complete the project.
Of that amount, $5.4 million has already been spent from the original appropriation.
This includes the purchase of 135 King Street and previous designs, studies, engineering, project management, and architects.
The Town still has $5.0 million available from the original appropriation.
A balance of $5,000,000 remains available from the original appropriation
The amount being requested at Town Meeting is $20.9 million.
This request, combined with the remaining $5.0 million, will allow the Town to complete the project.
Savings from plan reductions are directly impacted by rising construction costs over time and additional design + OPM fees.